Our Client, an international beverage manufacturer, needed to expand their production facilities, as the existing plant faced capacity limitations.
Following completion, WEW Engineering successfully optimised the plant. It is now meeting the current and future capacity requirements, with a high level of automation and data acquisition while obtaining the more onerous discharge Licence Limits.
Project Elements:
- New balance tank
- New High-Level pH correction system
- Revised aeration system operation
- New chemical DAF unit with coagulant dosing, polymer dosing, & flocculation
- Sludge tank & pumps
- PLC/SCADA upgrade
- A backup MBR system