Curraleigh West to Midleton Pipeline Co. Tipperary & Co. Cork

The Curraleigh West to Midleton Gas Pipeline is a 600mmdiameter, fully welded steel pipeline which runs approximately 47km cross country from Curraleigh West AGI on the existing Cork-Dublin Pipeline to Midleton Compressor Station on th outskirts of Midleton Co. Cork. The pipeline is required in order to reinforce and secure the supply of natural gas in the [...]

Gormanston Gas Interconnector Station

Murphy International Ltd in conjunction with Fingleton White & Co. Ltd., were awarded the Engineer / Procure / Construct (EPC) Contract for the Interconnector Receiving Station at Gormanston, Co. Meath. The station included filtering, metering, heating, regulation and pigging facilities complete with control and instrumenta- tion systems. To facilitate these requirements there were 4 no. buildings within [...]

Supplying Natural Gas to the 400MW Coolkeeragh CCGT Power Station

The North-West Pipeline is a 450mm diameter, fully welded steel pipeline which runs approximately 112km across country from Carrickfergus Co. Antrim to Coolkeeragh Co. Derry. The pipeline is designed to transmit 200,000 Standard Cubic Meters of Natural Gas per hour (2,027 MW) at a maximum pressure of 85bar. The pipeline design includes an off-take station and hot-tap from [...]

Fingleton White implement Industrial and Commercial Meter Replacement Project on behalf of Bord Gais Network

Fingleton White were appointed by Bord Gais Networks to project manage the replacement and upgrade of 1631 industrial / commercial meter installations in Dublin, Cork, Limerick, Clare ,Tipperary, Waterford, Carlow, Cavan, Kildare, Kilkenny, Louth, Meath, Wicklow and Monaghan. This includes the site survey, design and completion of assest capture records. The project scope covered I/C installations operating at [...]

Pipeline to Aughinish Co. Limerick, Ireland.

Bord Gáis Éireann awarded the project management of a 6km pipeline to supply Aughinish Alumina. This included the design, material procurement, and planning of the pipeline and an above ground gas installation.The pipeline is 6km in length and constructed from 300NB continuously welded carbon steel pipe. The pipeline design pressure is 85 Bar with a flow of [...]